Celebrating the Completion of SFO Westfield Cargo Building

The new West Field Cargo Redevelopment Facility replaced a 40-year-old existing cargo building at San Francisco International Airport (SFO). It was completed in August of 2014 and is ready to accommodate tenants in the logistics arena. The cargo area is approximately 62,000 square feet, with a clear height of 30 feet. The two office pods, each two stories tall, total about 14,000 square feet. After demolition of the old building, site improvements included the airline operating area (AOA) and adjoining hardstand, the loading dock side and access, and a new raised floor elevation for the facility to accommodate future ocean level rise. SFO proceeded on this project in a design/build delivery method. Cornerstone staff played a vital role on the project by providing Project Management Support Services for the whole project duration of 16 months. The $35 million project was completed on time and within budget.